2022 Capital Improvement Projects

To access the interactive tentative 2022 CIP location map: Click Here

To access a PDF version of the 2022 CIP location map: Click Here

ROAD CONSTRUCTION (CAPITAL) 
 
Project Start/End Budget Amount Award Amount % Complete
Road Program Aug/Nov $2,940,000 $2,852,651 99%
Brick Street Reconstruct. (Forest Ave) Sep/Dec 99%
Alley Program Sep/Dec $576,000 $663,982 99%
Ouilmette Way Alley Project Aug/Dec $150,000 $515,354 90%
Brick Street Renovation (16th St) Aug/Dec $390,000 $480,083 99%
Parking Lot Improvements 2023 $272,000 Postponed
ROAD CONSTRUCTION (MAINTENANCE)
Project Start/End Budget Amount Award Amount % Complete
Asphalt Patching May/Nov $98,000 $125,800 100%
Sidewalk & Curb Replacement Jul/Nov $77,000 $97,000 99%
Sidewalk Grinding Jun/Jul $19,373 $19,373 100%
Crack Sealing Jul/Jul $27,000 $27,000 100%
Pavement Marking 2023 $54,000 Postponed
Pavement Rejuvenation Aug/Aug $80,000 $52,200 100%
Brick Sidewalk Maintenance Sep/Oct $15,000 Postponed
Brick Street Maintenance Dec $116,000 $104,000 20%
Sidewalk Mudjacking 2023 $10,000 Postponed
         
UTILITY CONSTRUCTION (CAPITAL) 
Project Start/End Budget Amount Award Amount % Complete
NSP (Phase 3)        Mar/      Jun ’23 $28,400,000 $21,352,745 95%
 
UTILITY CONSTRUCTION (MAINTENANCE)   
Project Start/End Budget Amount Award Amount % Complete
Sewer Cleaning and Televising Mar/Aug $240,000 $240,000 99%
Utility Patching May/Dec $60,000 (Sewer)

$78,000 (Water)

$50,000 (Sewer)

$78,000 (Water)

100% (Asphalt);

100% (Concrete);

99% (Brick)

Sewer Lining Jul/Dec $720,000 $706,626 95%
Sewer Repair and Valve Installation 2023 $554,000 Postponed 0%
         
DESIGN SERVICES        
Project Start/End Budget Amount Award Amount % Complete
Phase II Design – Wilmette Avenue Resurfacing Mar/Jan’23 $260,000 $56,500 95%
Phase II Design – Skokie & Lake Intersection Improvements    May/     Mar ’23 $266,830 $135,256 85%
Phase II Design – Skokie Blvd Path Dec/TBD TBD 0%
Phase II Design – Skokie Valley Trail Oct ‘22/
2024
 
$50,500  $50,500  10%
MBATP Feasibility Study
Jul/   Spring ’23 $120,000 TBD 65%

 

(Data above reflects progress as of November 30, 2022.)

This page was last updated December 19, 2022.