Asphalt to Brick Street Reconstruction
Contractor: A Lamp Concrete Contractor, Inc.
Project Contact: Jorge Cruz, P.E., Assistant Village Engineer, cruzj@wilmette.com or 847-853-7623
Background
The purpose of this project is to restore an existing brick street block that currently has a very poor or worse asphalt overlay. The typical scope of work consists of removing the asphalt surface, replacing the concrete curb, placing a new stone base, and relaying the existing bricks. The work also includes intermittent sidewalk repairs, minor sewer repairs, and parkway
restoration.
The asphalt-to-brick reconstruction of Forest Avenue (900 block to Wilmette Ave) is scheduled for reconstruction in 2022.
Schedule
Tentative Start: July 2022
Tentative Completion: September 2022
Downloads
Brick Street Renovation
Contractor: A Lamp Concrete Contractors, Inc.
Project Contact: Jorge Cruz, P.E., Assistant Village Engineer, cruzj@wilmette.com or 847-853-7623
Background
The purpose of this project is to rehabilitate an existing brick street block that is rated in very poor condition. The scope of work consists of removing the existing brick pavers, replacing the concrete curb, placing new stone, and relaying the existing bricks. The work also includes intermittent sidewalk repairs, minor sewer repairs, and parkway restoration.
Two blocks of 16th Street, from Wilmette Avenue to Washington Avenue, are included in the bid and scheduled for renovation in 2022.
Schedule
Tentative Start: August 2022
Tentative Completion: September 2022
Downloads
Brick Sidewalk Maintenance
Contractor: A Lamp Concrete Contractor, Inc.
Project Contact: Jorge Cruz, P.E., Assistant Village Engineer, cruzj@wilmette.com or 847-853-7623
Background
This project repairs areas of settled decorative brick sidewalk pavers in the business districts with the goal to improve walkway safety and reduce liability.
Schedule
Tentative Start: September 2022
Tentative Completion: October 2022
Downloads
Brick Street Maintenance
Contractor: A Lamp Concrete Contractor, Inc.
Project Contact: Jorge Cruz, P.E., Assistant Village Engineer, cruzj@wilmette.com or 847-853-7623
Background
This project repairs areas of settled brick street pavers at various locations with the goal to improve rideability and safety and reduce liability.
Schedule
Tentative Start: September 2022
Tentative Completion: October 2022