2022 Brick Program

Asphalt to Brick Street Reconstruction

Contractor: A Lamp Concrete Contractor, Inc.

Project Contact: Jorge Cruz, P.E., Assistant Village Engineer, cruzj@wilmette.com or 847-853-7623

Background

The purpose of this project is to restore an existing brick street block that currently has a very poor or worse asphalt overlay. The typical scope of work consists of removing the asphalt surface, replacing the concrete curb, placing a new stone base, and relaying the existing bricks. The work also includes intermittent sidewalk repairs, minor sewer repairs, and parkway
restoration.

The asphalt-to-brick reconstruction of Forest Avenue (900 block to Wilmette Ave) is scheduled for reconstruction in 2022.

Schedule

Tentative Start: July 2022

Tentative Completion: September 2022

Downloads


Brick Street Renovation

Contractor: A Lamp Concrete Contractors, Inc.

Project Contact: Jorge Cruz, P.E., Assistant Village Engineer, cruzj@wilmette.com or 847-853-7623

Background

The purpose of this project is to rehabilitate an existing brick street block that is rated in very poor condition. The scope of work consists of removing the existing brick pavers, replacing the concrete curb, placing new stone, and relaying the existing bricks. The work also includes intermittent sidewalk repairs, minor sewer repairs, and parkway restoration.

Two blocks of 16th Street, from Wilmette Avenue to Washington Avenue, are included in the bid and scheduled for renovation in 2022.

Schedule

Tentative Start: August 2022

Tentative Completion: September 2022

Downloads


Brick Sidewalk Maintenance

Contractor: A Lamp Concrete Contractor, Inc.

Project Contact: Jorge Cruz, P.E., Assistant Village Engineer, cruzj@wilmette.com or 847-853-7623

Background

This project repairs areas of settled decorative brick sidewalk pavers in the business districts with the goal to improve walkway safety and reduce liability.

Schedule

Tentative Start: September 2022

Tentative Completion: October 2022

Downloads


Brick Street Maintenance

Contractor: A Lamp Concrete Contractor, Inc.

Project Contact: Jorge Cruz, P.E., Assistant Village Engineer, cruzj@wilmette.com or 847-853-7623

Background

This project repairs areas of settled brick street pavers at various locations with the goal to improve rideability and safety and reduce liability.

Schedule

Tentative Start: September 2022

Tentative Completion: October 2022