Capital Improvement Projects for 2020

Please click here for a PDF of this year’s CIP project locations.

Please use this CIP interactive map for additional information.

 

ROAD PROJECTS (CAPITAL)

Project Start/End % Complete Budget Amount Award Amount Final Amount
Road Program May/Sept 90% $2,920,000 $2,344,369
Alley Program June/Oct 90% $450,000 $409,700
Central Avenue & Downtown Streetscape Aug ‘20/

Sept ‘21

5% $2,613,260 est.

(General)

$2,323,316 est.

(Water)

$3,079,564

(General)

$2,016,009

(Water)

Brick Street Recon (Forest) July/Sept 85% Incl in Alley Program $339,272

 

ROAD MAINTENANCE

Project Start/End % Complete Budget Amount Award Amount Final Amount
Brick Repairs Sept/Oct 0% $110,000 $67,100
Sidewalk/Curb April/August 95% $80,000 $80,000
Pavement Patching May/Oct 65% $92,000 $92,000
Pavement Marking Sept/Oct 0% $37,000 $37,000
Crack Sealing April 100% $25,000 $25,000 $25,000
Pavement Rejuvenation August 100% $19,000 $19,000 $17,945

 

SEWER PROJECTS (CAPITAL)

Project Start/End % Complete Budget Amount Award Amount Final Amount
NSP (Phase 1A) Oct ‘19/July ‘20 95% $23,210,000 $4,211,539
NSP (Phase 1) April/Nov 95% Incl above $12,750,177

 

WATER PROJECTS (CAPITAL)

Project Start/End % Complete Budget Amount Award Amount Final Amount
Water Main Replacement (Lake Avenue) July/September 85% $440,425 (2019) $777,653

 

SEWER / WATER PROJECTS (MAINTENANCE)

Project Start/End % Complete Budget Amount Award Amount Final Amount
Sewer Cleaning and Televising April/September 55% $234,500 $234,500
Utility Patching April/Oct 60%  

$65,000 (Sewer)

 

$80,000 (Water)

 

$70,925     (Asphalt)

$45,000 (Concrete)

$29,000 (Brick)

Sewer Lining Dec/Jan ’21 0% $820,000 TBD
Sewer Repair and Valve Installation Oct/Nov 0% $425,000 TBD

 

This page was last updated September 8, 2020.